Application of duration measure in quantifying the sensitivity of project returns to changes in discount rates
| Author | Affiliation |
|---|---|
Yousefi, Vahidreza | University of Tehran |
Yakhchali, Siamak Haji | University of Tehran |
| Year | Volume | Issue | Start Page | End Page |
|---|---|---|---|---|
2019 | 9 | 13 | 1 | 14 |
| URI | Access Rights |
|---|---|
| https://hdl.handle.net/20.500.14911/122651 | |
| https://doi.org/10.3390/admsci9010013 | Viso teksto dokumentas (atviroji prieiga) / Full Text Document (Open Access) |
| https://www.mdpi.com/2076-3387/9/1/13 | Viso teksto dokumentas (atviroji prieiga) / Full Text Document (Open Access) |
| https://talpykla.elaba.lt/elaba-fedora/objects/elaba:34033043/datastreams/MAIN/content |
In this research, the concept of Duration with a new application in project management has been defined. The Duration of each project provides the project manager with a combined measure containing concepts of return, cost and time of the project. Further in this article, the changes in project return, based on different assumptions such as discount rate, have been examined. To examine the effect of the changes in these factors, the Monte Carlo simulation has been used. The relationship between these factors is nonlinear which reflects the great importance of investment on appropriate risk management systems. The data from a set of construction projects have been used in order to verify the results of this study. Similar relationships can be expected to exist in other industries as well.
This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (http://creativecommons.org/licenses/by/4.0/).